CompTIA
PK0-004 · Question #658
PK0-004 Question #658: Real Exam Question with Answer & Explanation
The correct answer is A: Validate the change.. After implementing an approved change, the immediate next step is to validate that the change was implemented correctly and achieved the intended outcome before updating logs or closing the change.
Question
A project team has just implemented an approved change to a project. Which of the following should occur NEXT?
Options
- AValidate the change.
- BEvaluate the impact of the change.
- CImplement a regression plan.
- DUpdate the issue log.
Explanation
After implementing an approved change, the immediate next step is to validate that the change was implemented correctly and achieved the intended outcome before updating logs or closing the change.
Common mistakes.
- B. Evaluating the impact of the change should have been done before approval, during the change request analysis phase - not after implementation.
- C. A regression plan is implemented if the change causes unintended side effects, which can only be determined after validation occurs.
- D. Updating the issue log may be appropriate if the change was implemented in response to an issue, but validating the change must happen first to confirm resolution.
Concept tested. Post-implementation change validation
Reference. https://www.pmi.org/learning/library/change-control-process-project-management-9050
Community Discussion
No community discussion yet for this question.