While working on a project, a self-organized team determines what will be accomplished during the next two weeks. Which of the following describes what the team is doing?

The correct answer is C. Sprint planning. A sprint, which is a time-bound period of work, always starts with a sprint planning meeting. During the meeting, team members choose items from the backlog to work on during the sprint. The backlog is a list of requirements (both functional and nonfunctional) for the project…

Project life cycle phases

Question

While working on a project, a self-organized team determines what will be accomplished during the next two weeks. Which of the following describes what the team is doing?

Options

  • ACreating a WBS
  • BGathering continuous requirements
  • CSprint planning
  • DHolding a Scrum meeting

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    91% (41)
  • D
    2% (1)

Explanation

A sprint, which is a time-bound period of work, always starts with a sprint planning meeting. During the meeting, team members choose items from the backlog to work on during the sprint. The backlog is a list of requirements (both functional and nonfunctional) for the project. The product owner prioritizes the backlog items based on business need, risk, and value to the organization. The Scrum team members break down large requirements into manageable portions of work that can be completed in a sprint.

Topics

#sprint planning#agile#Scrum#iterative development