PK0-004 · Question #656

A first-time project manager is developing a project charter. Which of the following are key elements to have the project charter approved? (Choose two.)

The correct answer is B. Business case D. Requirements. A Business Case and High-level Requirements are included in the project charter.

Tools and documentation

Question

A first-time project manager is developing a project charter. Which of the following are key elements to have the project charter approved? (Choose two.)

Options

  • AProject team
  • BBusiness case
  • CDetailed risks
  • DRequirements
  • EService-level agreement
  • FDetailed budget

How the community answered

(38 responses)
  • B
    95% (36)
  • E
    3% (1)
  • F
    3% (1)

Explanation

A Business Case and High-level Requirements are included in the project charter.

Topics

#project charter#business case#requirements#project initiation