CompTIA
PK0-004 · Question #656
A first-time project manager is developing a project charter. Which of the following are key elements to have the project charter approved? (Choose two.)
The correct answer is B. Business case D. Requirements. A Business Case and High-level Requirements are included in the project charter.
Tools and documentation
Question
A first-time project manager is developing a project charter. Which of the following are key elements to have the project charter approved? (Choose two.)
Options
- AProject team
- BBusiness case
- CDetailed risks
- DRequirements
- EService-level agreement
- FDetailed budget
How the community answered
(38 responses)- B95% (36)
- E3% (1)
- F3% (1)
Explanation
A Business Case and High-level Requirements are included in the project charter.
Topics
#project charter#business case#requirements#project initiation