PK0-004 · Question #496
A customer is in the early planning stages of a technology rebuild. To gain a better understanding of the possible solutions, which of the following documents should the customer send to prospective…
The correct answer is C. RFI. Request for Information (RFI): An RFI is used when you need to gather more information about the goods or services you need to procure. This process will give you a sense for the number of providers or contractors who can provide the goods or services, and you will get an idea…
Question
A customer is in the early planning stages of a technology rebuild. To gain a better understanding of the possible solutions, which of the following documents should the customer send to prospective vendors?
Options
- ARFP
- BRFQ
- CRFI
- DSOW
How the community answered
(32 responses)- A3% (1)
- B6% (2)
- C91% (29)
Explanation
Request for Information (RFI): An RFI is used when you need to gather more information about the goods or services you need to procure. This process will give you a sense for the number of providers or contractors who can provide the goods or services, and you will get an idea of cost. An RFI or RFQ is used when the costs are unknown to you and you need an estimate for the goods or services.
Topics
Community Discussion
No community discussion yet for this question.