Question

A busy project manager has a diverse set of stakeholders and team members with respect to age and cultural background. Which of the following is the BEST method for communicating to the project manager's audiences?

Options

  • ASpeak with each individual, and communicate with that individual according to stated and
  • BUtilize a variety of communication methods, such as email, IM, conference calls, and face-to-
  • CDevelop a communications plan that considers the individual's impact on the project and
  • DDetermine a single best communication method to provide efficient and consistent