PK0-004 · Question #498
A project manager is assigned to a project with an unfamiliar domain area. The project manager is compiling a list of stakeholders and their roles in a chart. The project manager lists SMEs in the…
The correct answer is C. consulted. In a RACI matrix (Responsible, Accountable, Consulted, Informed), Subject Matter Experts (SMEs) are classified as 'Consulted.' Because the project manager is unfamiliar with the domain, SMEs are brought in to provide expert knowledge and guidance-they give input and are asked…
Question
A project manager is assigned to a project with an unfamiliar domain area. The project manager is compiling a list of stakeholders and their roles in a chart. The project manager lists SMEs in the project domain to be:
Options
- Adelegated
- Binstructed
- Cconsulted
- Demployed
How the community answered
(48 responses)- A2% (1)
- B6% (3)
- C88% (42)
- D4% (2)
Explanation
In a RACI matrix (Responsible, Accountable, Consulted, Informed), Subject Matter Experts (SMEs) are classified as 'Consulted.' Because the project manager is unfamiliar with the domain, SMEs are brought in to provide expert knowledge and guidance-they give input and are asked for their expertise, but they do not perform the work directly. They are not delegated tasks (that implies ownership of deliverables), not simply instructed (that implies they follow orders), and 'employed' is not a RACI category. 'Consulted' is the correct RACI role for advisory stakeholders whose knowledge is needed.