PK0-004 · Question #495
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts…
The correct answer is C. December 20. Task A 15th to 16th + Task C 17-19 Dec - So task D starts on Day 20.
Project life cycle phases
Question
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
Options
- ADecember 18
- BDecember 19
- CDecember 20
- DDecember 21
- EDecember 22
How the community answered
(35 responses)- A9% (3)
- B3% (1)
- C69% (24)
- D17% (6)
- E3% (1)
Explanation
Task A 15th to 16th + Task C 17-19 Dec - So task D starts on Day 20.
Topics
#task dependencies#schedule calculation#critical path#project scheduling