Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts…

The correct answer is C. December 20. Task A 15th to 16th + Task C 17-19 Dec - So task D starts on Day 20.

Project life cycle phases

Question

Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?

Options

  • ADecember 18
  • BDecember 19
  • CDecember 20
  • DDecember 21
  • EDecember 22

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    69% (24)
  • D
    17% (6)
  • E
    3% (1)

Explanation

Task A 15th to 16th + Task C 17-19 Dec - So task D starts on Day 20.

Topics

#task dependencies#schedule calculation#critical path#project scheduling