CompTIA
PK0-004 · Question #491
A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager…
The correct answer is D. Consult the communications plan and act accordingly. Check the communication plan. If the stakeholder is down as having only monthly updates, it might need to be updated or verified with the stakeholder.
Tools and documentation
Question
A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
Options
- AImmediately send the current weekly status report
- BAdd email to the distribution list for the weekly status report
- CRemove email from the distribution list for the monthly status report
- DConsult the communications plan and act accordingly
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C11% (3)
- D79% (22)
Explanation
Check the communication plan. If the stakeholder is down as having only monthly updates, it might need to be updated or verified with the stakeholder.
Topics
#communications plan#status reporting#distribution list#stakeholder communication
Community Discussion