PK0-004 Question #491: Real Exam Question with Answer & Explanation

The correct answer is D: Consult the communications plan and act accordingly. Check the communication plan. If the stakeholder is down as having only monthly updates, it might need to be updated or verified with the stakeholder.

Question

A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?

Options

  • AImmediately send the current weekly status report
  • BAdd email to the distribution list for the weekly status report
  • CRemove email from the distribution list for the monthly status report
  • DConsult the communications plan and act accordingly

Explanation

Check the communication plan. If the stakeholder is down as having only monthly updates, it might need to be updated or verified with the stakeholder.