A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized. Which of the following is the NEXT appropriate step for the project manager to take?

Exhibit

PK0-004 question #490 exhibit

Options

  • AIdentify risk strategies for the realized events
  • BChange the risk status to closed for 2 and 6
  • CConsult the risk management plan
  • DUpdate the issue log