Question
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized. Which of the following is the NEXT appropriate step for the project manager to take?
Exhibit
Options
- AIdentify risk strategies for the realized events
- BChange the risk status to closed for 2 and 6
- CConsult the risk management plan
- DUpdate the issue log