PK0-004 · Question #492
PK0-004 Question #492: Real Exam Question with Answer & Explanation
The correct answer is B: Functional. In a functional organizational structure, employees report to functional managers who have full authority over resource allocation. A functional manager can reassign team members to other projects or assignments without the project manager's approval - which is exactly what is ha
Question
Options
- AProjectized
- BFunctional
- CFlat
- DStrong matrix
Explanation
In a functional organizational structure, employees report to functional managers who have full authority over resource allocation. A functional manager can reassign team members to other projects or assignments without the project manager's approval - which is exactly what is happening here. In a projectized structure (A), the project manager has full authority over the team. In a strong matrix (D), the project manager has significant influence over resources. A flat organization (C) is not a standard PMI structure classification. The loss of a team member to a higher-priority assignment signals a functional org.
Community Discussion
No community discussion yet for this question.