PK0-004 · Question #492
A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager…
The correct answer is B. Functional. In a functional organizational structure, employees report to functional managers who have full authority over resource allocation. A functional manager can reassign team members to other projects or assignments without the project manager's approval - which is exactly what is…
Question
A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work?
Options
- AProjectized
- BFunctional
- CFlat
- DStrong matrix
How the community answered
(50 responses)- A6% (3)
- B90% (45)
- C2% (1)
- D2% (1)
Explanation
In a functional organizational structure, employees report to functional managers who have full authority over resource allocation. A functional manager can reassign team members to other projects or assignments without the project manager's approval - which is exactly what is happening here. In a projectized structure (A), the project manager has full authority over the team. In a strong matrix (D), the project manager has significant influence over resources. A flat organization (C) is not a standard PMI structure classification. The loss of a team member to a higher-priority assignment signals a functional org.