nerdexam
CompTIA

PK0-004 · Question #493

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The…

The correct answer is A. Take the request to the CCB. The PM needs to first evaluate the impact the changes may have, then send it to be reviewed by

Project management concepts

Question

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes. Which of the following BEST describes how the project manager should respond?

Options

  • ATake the request to the CCB
  • BQuickly make the changes
  • CAsk a project team member to make the changes
  • DInform the sponsor of the stakeholder's request

How the community answered

(33 responses)
  • A
    76% (25)
  • B
    15% (5)
  • C
    3% (1)
  • D
    6% (2)

Explanation

The PM needs to first evaluate the impact the changes may have, then send it to be reviewed by

Topics

#change control board#scope management#change request process#stakeholder requests

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice