A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the…

The correct answer is C. Project charter. A project charter is the statement of scope, objectives and people who are participating in a project. It begins the process of defining the roles and responsibilities of those participants and outlines the objectives and goals of the project. The charter also identifies the…

Tools and documentation

Question

A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?

Options

  • AProject schedule
  • BProject management plan
  • CProject charter
  • DStaffing matrix

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    4% (1)
  • C
    89% (25)

Explanation

A project charter is the statement of scope, objectives and people who are participating in a project. It begins the process of defining the roles and responsibilities of those participants and outlines the objectives and goals of the project. The charter also identifies the main stakeholders and defines the authority of the project manager.

Topics

#project charter#resource management#PM authority#project documentation