PK0-004 · Question #471
A project manager is collecting the number of hours, the resources, and the amount of money spent on hardware and software. Which of the following is MOST likely the purpose of collecting this…
The correct answer is D. Expenditure tracking. Collecting the number of hours worked, resources utilized, and costs incurred on hardware and software is the definition of expenditure tracking (D). This activity monitors actual spending against the project budget to ensure costs are within approved limits and to provide an…
Question
A project manager is collecting the number of hours, the resources, and the amount of money spent on hardware and software. Which of the following is MOST likely the purpose of collecting this information?
Options
- AFinancial stability
- BCompetitive advantage
- CBudget constraints
- DExpenditure tracking
How the community answered
(18 responses)- B6% (1)
- C6% (1)
- D89% (16)
Explanation
Collecting the number of hours worked, resources utilized, and costs incurred on hardware and software is the definition of expenditure tracking (D). This activity monitors actual spending against the project budget to ensure costs are within approved limits and to provide an audit trail. Financial stability (A) is a broad organizational concept, not a project-level tracking objective. Competitive advantage (B) refers to strategic market positioning, which is unrelated to recording project expenditures. Budget constraints (C) are inputs that define spending limits; they are a parameter, not the purpose of collecting actual cost data.
Topics
Community Discussion
No community discussion yet for this question.