PK0-004 · Question #472
A project sponsor wants to know which tasks are next in the project but is unable to find this information. Which of the following may need to be adjusted?
The correct answer is B. Status report. Status Reports, according to CompTIA, are a summary of activities over a cumulative period of time, such as year-to-date or since the start of a project. Since the PM is seeking information regarding what's next and is unable to find it, he should make a note in the Issue Log…
Question
A project sponsor wants to know which tasks are next in the project but is unable to find this information. Which of the following may need to be adjusted?
Options
- AScope document
- BStatus report
- CIssue log
- DRisk log
How the community answered
(52 responses)- A4% (2)
- B94% (49)
- D2% (1)
Explanation
Status Reports, according to CompTIA, are a summary of activities over a cumulative period of time, such as year-to-date or since the start of a project. Since the PM is seeking information regarding what's next and is unable to find it, he should make a note in the Issue Log. We are already beyond the point of this being a Risk, since the document he should be referencing for these items does not exist. Raise the problem in the Issue log so you can address it by creating the missing materials.
Topics
Community Discussion
No community discussion yet for this question.