A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?

The correct answer is C. Closure. Closure is where you discuss lessons learned, accomplishments, and project summary. Status isn't a communication method.

Project life cycle phases

Question

A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?

Options

  • AKickoff
  • BImpromptu
  • CClosure
  • DStatus

How the community answered

(67 responses)
  • A
    1% (1)
  • B
    4% (3)
  • C
    87% (58)
  • D
    7% (5)

Explanation

Closure is where you discuss lessons learned, accomplishments, and project summary. Status isn't a communication method.

Topics

#lessons learned#closure meeting#retrospective#project closure