PK0-004 · Question #45
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule…
The correct answer is D. Status report. A status report consolidates project health information including percent complete, schedule progress, and budget - making it the primary reference when no handover meeting occurred.
Question
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?
Options
- AProject schedule
- BBalanced scorecard
- CIssue log
- DStatus report
How the community answered
(40 responses)- B3% (1)
- C3% (1)
- D95% (38)
Why each option
A status report consolidates project health information including percent complete, schedule progress, and budget - making it the primary reference when no handover meeting occurred.
A project schedule shows task timelines and dependencies but does not include budget constraints or a rolled-up percent completion summary.
A balanced scorecard is a strategic performance management framework used at the organizational level, not a project-level document tracking schedule or budget progress.
An issue log records problems and risks that arise during the project but does not contain schedule progress or budget status information.
A status report is a comprehensive project document that captures percent of completion, schedule progress, and budget constraints in a single snapshot. It is specifically designed to communicate overall project performance to stakeholders and is the standard artifact a new project manager would consult to quickly understand current project standing. Unlike other documents, it aggregates the exact three data points referenced in the question.
Concept tested: Identifying the correct project status reporting document
Source: https://www.pmi.org/learning/library/monitoring-controlling-process-group-project-management-6077