The correct answer is C: D, E, H. 12 weeks. Longest path is correct answer using Critical Path method.

Question

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?

Options

  • AA, C, G
  • BA, B, F
  • CD, E, H
  • DD, B, F

Explanation

12 weeks. Longest path is correct answer using Critical Path method.