There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are…

The correct answer is C. D, E, H. 12 weeks. Longest path is correct answer using Critical Path method.

Tools and documentation

Question

There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?

Options

  • AA, C, G
  • BA, B, F
  • CD, E, H
  • DD, B, F

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    8% (4)
  • C
    75% (38)
  • D
    14% (7)

Explanation

12 weeks. Longest path is correct answer using Critical Path method.