PK0-004 · Question #44
PK0-004 Question #44: Real Exam Question with Answer & Explanation
The correct answer is C: D, E, H. 12 weeks. Longest path is correct answer using Critical Path method.
Question
There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?
Options
- AA, C, G
- BA, B, F
- CD, E, H
- DD, B, F
Explanation
12 weeks. Longest path is correct answer using Critical Path method.