PK0-004 · Question #43
A stakeholder is unaware of a project's status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
The correct answer is A. Status report E. Communication plan. They have information on the status (A) and which Stakeholders are informed (E) about the It is true that RACI is generally used to provide clarity on the roles and responsibilities assigned to each project team member, but these members are not necessarily informed.
Question
A stakeholder is unaware of a project's status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
Options
- AStatus report
- BOrganizational chart
- CRAO matrix
- DMeeting minutes
- ECommunication plan
How the community answered
(57 responses)- A93% (53)
- B4% (2)
- C2% (1)
- D2% (1)
Explanation
They have information on the status (A) and which Stakeholders are informed (E) about the It is true that RACI is generally used to provide clarity on the roles and responsibilities assigned to each project team member, but these members are not necessarily informed.
Topics
Community Discussion
No community discussion yet for this question.