PK0-004 · Question #444
A project manager determines deliverables are not meeting customer specifications. During which of the following project phases is this determination MOST likely to happen?
The correct answer is A. Monitor and control. The Monitor and Control phase is where the project manager continuously tracks, reviews, and regulates project progress and performance against the project management plan. Comparing deliverables to customer specifications-and identifying variances-is a core monitoring…
Question
A project manager determines deliverables are not meeting customer specifications. During which of the following project phases is this determination MOST likely to happen?
Options
- AMonitor and control
- BExecution
- CClosing
- DPlanning
How the community answered
(37 responses)- A92% (34)
- C5% (2)
- D3% (1)
Explanation
The Monitor and Control phase is where the project manager continuously tracks, reviews, and regulates project progress and performance against the project management plan. Comparing deliverables to customer specifications-and identifying variances-is a core monitoring activity. While execution is when deliverables are produced, it is the monitor and control phase that provides the structured oversight to detect that those deliverables fall short of requirements.
Topics
Community Discussion
No community discussion yet for this question.