During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?

The correct answer is C. Risk register. Risk register - It identifies potential risks, level of impact and suggests actions to take in the likelihood of event.

Tools and documentation

Question

During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?

Options

  • AIncident response
  • BProject plan
  • CRisk register
  • DBusiness continuity plan

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    8% (4)
  • C
    69% (34)
  • D
    18% (9)

Explanation

Risk register - It identifies potential risks, level of impact and suggests actions to take in the likelihood of event.

Topics

#risk register#CCB#change control#risk management