The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?
The correct answer is B. Initiation to planning. Once the project is approved and it moves into the planning stage, risks are identified with each major group of activities. A risk breakdown structure (RBS) can be used to identify increasing levels of detailed risk analysis.
Project life cycle phases
Question
The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?
Options
- AExecution to monitor and control
- BInitiation to planning
- CInitiation to monitor and control
- DPlanning to execution
How the community answered
(40 responses)- A3% (1)
- B75% (30)
- C8% (3)
- D15% (6)
Explanation
Once the project is approved and it moves into the planning stage, risks are identified with each major group of activities. A risk breakdown structure (RBS) can be used to identify increasing levels of detailed risk analysis.
Topics
#risk management#project phases#initiation#planning