PK0-004 · Question #427
A team member has reported Task 3 will be completed ahead of schedule. Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
The correct answer is D. 12 days. When Task 3 is completed in two days (ahead of schedule), it shortens or eliminates the path through Task 3, but the critical path shifts to a different, longer path through the network. Based on the referenced chart, even with Task 3 compressed to 2 days, another path through…
Question
A team member has reported Task 3 will be completed ahead of schedule. Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
Exhibits
Options
- A8 days
- B10 days
- C11 days
- D12 days
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C8% (2)
- D84% (21)
Explanation
When Task 3 is completed in two days (ahead of schedule), it shortens or eliminates the path through Task 3, but the critical path shifts to a different, longer path through the network. Based on the referenced chart, even with Task 3 compressed to 2 days, another path through the project still totals 12 days - making that the new critical path. The critical path is always the longest remaining path, and compressing one task can reveal a previously non-critical path as the new critical path. The answer of 12 days reflects the longest path that remains after Task 3's duration is reduced.