PK0-004 · Question #427

A team member has reported Task 3 will be completed ahead of schedule. Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

The correct answer is D. 12 days. When Task 3 is completed in two days (ahead of schedule), it shortens or eliminates the path through Task 3, but the critical path shifts to a different, longer path through the network. Based on the referenced chart, even with Task 3 compressed to 2 days, another path through…

Tools and documentation

Question

A team member has reported Task 3 will be completed ahead of schedule. Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

Exhibits

PK0-004 question #427 exhibit 1
PK0-004 question #427 exhibit 2
PK0-004 question #427 exhibit 3

Options

  • A8 days
  • B10 days
  • C11 days
  • D12 days

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    8% (2)
  • D
    84% (21)

Explanation

When Task 3 is completed in two days (ahead of schedule), it shortens or eliminates the path through Task 3, but the critical path shifts to a different, longer path through the network. Based on the referenced chart, even with Task 3 compressed to 2 days, another path through the project still totals 12 days - making that the new critical path. The critical path is always the longest remaining path, and compressing one task can reveal a previously non-critical path as the new critical path. The answer of 12 days reflects the longest path that remains after Task 3's duration is reduced.

Topics

#critical path#task duration#schedule analysis#network diagram

Community Discussion

No community discussion yet for this question.