Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B…

The correct answer is B. Six days. To find the critical path, trace all possible paths from start to finish and identify the longest one. Task A runs Days 1–2. Task B runs Days 3–4 (starts Day 3 independently). Task C starts after A (Day 3) and runs Days 3–5 (duration 3). Task D starts after BOTH B and C are…

Tools and documentation

Question

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?

Options

  • AFive days
  • BSix days
  • CSeven days
  • DEight days

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    72% (18)
  • C
    8% (2)
  • D
    16% (4)

Explanation

To find the critical path, trace all possible paths from start to finish and identify the longest one. Task A runs Days 1–2. Task B runs Days 3–4 (starts Day 3 independently). Task C starts after A (Day 3) and runs Days 3–5 (duration 3). Task D starts after BOTH B and C are complete; B finishes Day 4, C finishes Day 5, so D starts Day 6 and runs for 1 day, finishing Day 6. Path 1 (A→C→D): 2 + 3 + 1 = 6 days. Path 2 (B→D): B starts Day 3, so from project start it effectively spans days 3–4 then D on day 6 = 6 days total project duration. The critical path through A→C→D drives the project to completion at Day 6 (six days). Any delay on this path delays the project.

Topics

#critical path#task sequencing#network diagram#schedule calculation