PK0-004 · Question #295
Which of the following would be included in the project transition plan?
The correct answer is C. Maintenance responsibilities of the project deliverables. A project transition plan documents the handover of deliverables to operations, including who will be responsible for ongoing maintenance and support.
Question
Which of the following would be included in the project transition plan?
Options
- ASpecifications used for quality control measurements.
- BComparison of project deliverables with organizational strategic goals.
- CMaintenance responsibilities of the project deliverables.
- DAnalysis of the project expenditures.
How the community answered
(35 responses)- A3% (1)
- B3% (1)
- C86% (30)
- D9% (3)
Why each option
A project transition plan documents the handover of deliverables to operations, including who will be responsible for ongoing maintenance and support.
Specifications used for quality control measurements belong in the quality management plan, not the transition plan.
Comparing project deliverables with organizational strategic goals is part of the project selection process or business case documentation, not the transition plan.
Maintenance responsibilities for project deliverables are a core component of a transition plan because the plan defines how completed deliverables will be handed over from the project team to the operational or support teams. It ensures continuity by specifying who owns, maintains, and supports the deliverables after project closure. This is the primary purpose of transition planning - bridging project completion and ongoing operations.
Analysis of project expenditures belongs in financial reports or the project closure report, not the transition plan.
Concept tested: Project transition plan contents and purpose