PK0-004 Question #293: Real Exam Question with Answer & Explanation
The correct answer is B: provides a description of all of the components of a WBS, and a brief summary of its SOW, scope. A WBS dictionary is a document that describes each component of the WBS, including its scope of work, schedule milestones, and resource information.
Question
A WBS dictionary:
Options
- Ais a granular hierarchical breakdown of the work to be undertaken by the project team, to meet
- Bprovides a description of all of the components of a WBS, and a brief summary of its SOW, scope
- Callocates the WBS components to appropriate teams or named individuals within teams.
- Ddescribes how a project will be decomposed into smaller, manageable subprojects or work
Explanation
A WBS dictionary is a document that describes each component of the WBS, including its scope of work, schedule milestones, and resource information.
Common mistakes.
- A. A granular hierarchical breakdown of work to be undertaken describes the WBS (Work Breakdown Structure) itself, not the WBS dictionary.
- C. Allocating WBS components to teams or named individuals describes a Responsibility Assignment Matrix (RAM) or RACI chart, not a WBS dictionary.
- D. Describing how a project is decomposed into subprojects refers to the decomposition technique or the WBS creation process, not the WBS dictionary.
Concept tested. WBS dictionary purpose and contents
Reference. https://www.pmi.org/pmbok-guide-standards/lexicon