A team member has approached the project manager for an update on the project status and next tasks. Which of the following should the project manager do NEXT?
Options
- ASpeak with the team member's manager about their performance
- BResend the latest status report and project plan to the team member
- CReview the communications plan to determine why they were unaware
- DSend the communications plan to the team member