A new team has been put together for a construction project. The project currently does not have a cost estimate but the company has done other builds similar to the one at task and needs the…

The correct answer is A. Analogous. When historical data from similar projects exists and a quick estimate is needed, analogous estimating is the best approach because it leverages past actuals to produce a rapid high-level estimate.

Project management concepts

Question

A new team has been put together for a construction project. The project currently does not have a cost estimate but the company has done other builds similar to the one at task and needs the estimate at the end of the week. Which of the following approaches would be BEST to determine the cost?

Options

  • AAnalogous
  • BBottom up
  • CTop down
  • DExpert judgment

How the community answered

(41 responses)
  • A
    83% (34)
  • B
    5% (2)
  • C
    10% (4)
  • D
    2% (1)

Why each option

When historical data from similar projects exists and a quick estimate is needed, analogous estimating is the best approach because it leverages past actuals to produce a rapid high-level estimate.

AAnalogousCorrect

Analogous estimating uses actual cost data from previous similar projects as the basis for estimating the current project. Because the company has completed comparable builds, this approach is both feasible and fast, making it ideal when the estimate is required by end of week without detailed scope decomposition.

BBottom up

Bottom-up estimating requires a fully decomposed work breakdown structure and detailed task-level inputs, which takes significant time and is not feasible by end of week without a cost estimate already in place.

CTop down

Top-down is essentially synonymous with analogous estimating in most frameworks; however, as a distinct answer choice here it implies a less structured approach without the benefit of leveraging specific historical project data.

DExpert judgment

Expert judgment alone does not constitute a structured estimating technique and without supporting historical data or a defined method it would produce an unsupported figure.

Concept tested: Analogous cost estimating using historical project data

Source: https://www.pmi.org/learning/library/analogous-estimating-techniques-9078

Topics

#analogous estimating#cost estimation#historical data#time-constrained estimation