PK0-004 · Question #260
A project manager has been assigned to a software development solution at the ABC Inc. Which of the following should the sponsor expect within the scope document? (Select THREE).
The correct answer is C. Objectives F. Project exclusions H. Constraints. A scope document (scope statement) defines what is and is not included in the project, capturing objectives, exclusions, and constraints as its core components.
Question
Options
- ARisk register template
- BMilestones
- CObjectives
- DIssue log template
- EResource requirements
- FProject exclusions
- GCommunication expectations
- HConstraints
How the community answered
(40 responses)- A3% (1)
- B13% (5)
- C78% (31)
- E3% (1)
- G5% (2)
Why each option
A scope document (scope statement) defines what is and is not included in the project, capturing objectives, exclusions, and constraints as its core components.
A risk register template is part of the risk management plan, not the scope document.
Milestones are defined in the project schedule baseline, not the scope statement.
Objectives describe the measurable goals the project must achieve and are a fundamental component of the scope statement.
An issue log template belongs to the issue management or communications plan, not the scope document.
Resource requirements are captured in the resource management plan, not the scope statement.
Project exclusions explicitly state what is outside the project boundary, which is a defining purpose of the scope document and prevents scope creep.
Communication expectations belong in the communications management plan, not the scope document.
Constraints are limitations - such as budget, schedule, or regulatory requirements - that bound the project and must be documented in the scope statement.
Concept tested: Project scope statement required components
Source: https://www.pmi.org/learning/library/project-scope-statement-elements-components-6901