A project manager has been presented a set of documents containing why a project is needed, how it fits in with the company objectives, and the revenue that will be generated by the product. Which…
The correct answer is A. A business case. A business case justifies why a project should be undertaken by documenting the business need, strategic alignment, and expected financial return.
Question
A project manager has been presented a set of documents containing why a project is needed, how it fits in with the company objectives, and the revenue that will be generated by the product. Which of the following has the project manager just received?
Options
- AA business case
- BA charter
- CKey project deliverables
- DProject objectives
How the community answered
(24 responses)- A88% (21)
- B8% (2)
- C4% (1)
Why each option
A business case justifies why a project should be undertaken by documenting the business need, strategic alignment, and expected financial return.
The business case is the formal document that articulates the rationale for initiating a project, including the problem or opportunity being addressed, how the project aligns with organizational strategy, and the financial benefits such as revenue projections. It is used by sponsors and decision-makers to authorize or reject a project before a charter is issued.
A project charter formally authorizes the project and names the project manager, but it does not focus on the business justification or financial case.
Key project deliverables are the specific outputs or products the project will produce, not the justification for why the project exists.
Project objectives are measurable goals defined after project approval, not the strategic and financial rationale that precedes it.
Concept tested: Purpose and content of a business case
Source: https://www.pmi.org/learning/library/business-case-needs-assessment-initiation-11471