PK0-004 · Question #26

Which of the following metrics demonstrates to a project manager if a project is overspending or under spending ?

The correct answer is C. CPI. CPI (Cost Performance Index) is the earned value metric that directly quantifies whether a project is spending efficiently relative to the work accomplished, signaling overspending or underspending with a single ratio.

Tools and documentation

Question

Which of the following metrics demonstrates to a project manager if a project is overspending or under spending ?

Options

  • AEAC
  • BBAC
  • CCPI
  • DETC

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    88% (36)
  • D
    7% (3)

Why each option

CPI (Cost Performance Index) is the earned value metric that directly quantifies whether a project is spending efficiently relative to the work accomplished, signaling overspending or underspending with a single ratio.

AEAC

EAC (Estimate at Completion) forecasts the total expected cost of the project at completion and does not directly indicate whether current spending is efficient or inefficient relative to work accomplished.

BBAC

BAC (Budget at Completion) represents the total approved budget for the entire project and provides no information about current spending performance relative to the work that has been completed.

CCPICorrect

CPI is calculated as Earned Value (EV) divided by Actual Cost (AC), producing a ratio that measures cost efficiency at any point in the project. A CPI below 1.0 indicates the project is over budget for the work completed (overspending), while a CPI above 1.0 indicates the project is delivering more value than the cost incurred (underspending), making it the definitive metric for evaluating spending performance.

DETC

ETC (Estimate to Complete) represents the expected cost needed to finish the remaining project work and does not measure whether the project is currently over or under its planned spending rate.

Concept tested: CPI as cost efficiency and spending performance metric

Source: https://www.pmi.org/learning/library/earned-value-management-primer-7180

Topics

#CPI#earned value management#cost performance index#EVM metrics