PK0-004 · Question #27
A project manager is managing a transnational project. One of the key team members is having difficulties understanding the client requirements. Which of the following actions would be BEST for the…
The correct answer is D. Ask the client to provide requirements in the native language of the team. According to the book, hire a translator, find a common language, use translated written word rather than spoken to help prevent misunderstanding.
Project management concepts
Question
A project manager is managing a transnational project. One of the key team members is having difficulties understanding the client requirements. Which of the following actions would be BEST for the project manager to take?
Options
- AAsk the client to provide additional language resources to the team.
- BPurchase a language translation program
- CHire a translator to help the key team member
- DAsk the client to provide requirements in the native language of the team
How the community answered
(23 responses)- A4% (1)
- B13% (3)
- C4% (1)
- D78% (18)
Explanation
According to the book, hire a translator, find a common language, use translated written word rather than spoken to help prevent misunderstanding.
Topics
#communication management#transnational project#language barriers#client requirements