Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
The correct answer is D. Project stakeholders and project team. Changes must be communicated to team members, project sponsor, and project stakeholder.
Project management concepts
Question
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Options
- AProject manager and project scheduler
- BProject coordinator and project sponsor
- CProject champion and project scheduler
- DProject stakeholders and project team
How the community answered
(46 responses)- A2% (1)
- B7% (3)
- C2% (1)
- D89% (41)
Explanation
Changes must be communicated to team members, project sponsor, and project stakeholder.
Topics
#milestone#stakeholder communication#status reporting#project schedule