PK0-004 · Question #24
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs…
The correct answer is B. Initiate the regression plan. When an authorized change introduces a defect that pushes a Key Performance Parameter outside its acceptable threshold, the regression plan provides the structured procedure to roll back the change and restore the system to its last known compliant state.
Question
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs. Which of the following actions should the project manager take?
Options
- ASubmit a new change request.
- BInitiate the regression plan
- CAdd remediation to the schedule
- DAccept the new power output.
How the community answered
(30 responses)- A3% (1)
- B77% (23)
- C13% (4)
- D7% (2)
Why each option
When an authorized change introduces a defect that pushes a Key Performance Parameter outside its acceptable threshold, the regression plan provides the structured procedure to roll back the change and restore the system to its last known compliant state.
Submitting a new change request may be a subsequent step after regression is complete, but it does not immediately address the live defect currently keeping performance outside the KPPs.
A regression plan is a pre-defined procedure for reversing or rolling back a change that has produced unintended negative effects. Because the implemented change caused the building power output to fall outside the Key Performance Parameters (KPPs), initiating the regression plan addresses the active defect systematically by returning the system to its pre-change baseline and restoring compliance with defined performance requirements before any further action is taken.
Adding remediation to the schedule defers resolution of an active defect and bypasses the regression plan, which is the defined process for handling defects introduced by a change.
Accepting power output that falls outside defined KPPs violates the project performance requirements and cannot occur without a formal waiver or an approved change request modifying those parameters.
Concept tested: Initiating regression plan after change-induced KPP defect