A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects…

The correct answer is A. It is under budget. Cost Performance Index = Earned Value/Actual Cost

Tools and documentation

Question

A project manager is creating the monthly report for top management. The project manager has collected the information below:

AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?

Options

  • AIt is under budget.
  • BIt is over budget.
  • CIt is ahead of schedule.
  • DIt is behind schedule.

How the community answered

(67 responses)
  • A
    78% (52)
  • B
    6% (4)
  • C
    3% (2)
  • D
    13% (9)

Explanation

Cost Performance Index = Earned Value/Actual Cost

Topics