A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects…
The correct answer is A. It is under budget. Cost Performance Index = Earned Value/Actual Cost
Tools and documentation
Question
A project manager is creating the monthly report for top management. The project manager has collected the information below:
AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?
Options
- AIt is under budget.
- BIt is over budget.
- CIt is ahead of schedule.
- DIt is behind schedule.
How the community answered
(67 responses)- A78% (52)
- B6% (4)
- C3% (2)
- D13% (9)
Explanation
Cost Performance Index = Earned Value/Actual Cost
Topics
#earned value management#CPI#cost performance index#project metrics