In a project with a BAC of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
The correct answer is B. The project is over budget and ahead of schedule. The question states that the CPI is 0.80 which is less than 1.0 and that indicates that it's 'over budget'. The SPI is 1.20 which is greater than 1.0 which indicates that it's 'ahead of schedule'.
Tools and documentation
Question
In a project with a BAC of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
Options
- AThe project is under budget and ahead of schedule.
- BThe project is over budget and ahead of schedule.
- CThe project is under budget and behind schedule.
- DThe project is over budget and behind schedule.
How the community answered
(26 responses)- A15% (4)
- B73% (19)
- C4% (1)
- D8% (2)
Explanation
The question states that the CPI is 0.80 which is less than 1.0 and that indicates that it's 'over budget'. The SPI is 1.20 which is greater than 1.0 which indicates that it's 'ahead of schedule'.
Topics
#earned value management#CPI#SPI#schedule performance