A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?

Options

  • APareto chart
  • BFishbone diagram
  • CProcess diagram
  • DRun chart