A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:
The correct answer is B. tasks. Below are the steps for creating a schedule according to certify: 1. Determine Tasks 2. Sequence Tasks 3. Allocate resources 4. Determine task duration including start and end dates. 5. Determine milestones 6. Construct the schedule 7. Determine the critical path 8. Set the…
Question
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:
Options
- Adurations.
- Btasks.
- Ccritical path.
- Dresources.
How the community answered
(52 responses)- A2% (1)
- B90% (47)
- C2% (1)
- D6% (3)
Explanation
Below are the steps for creating a schedule according to certify: 1. Determine Tasks 2. Sequence Tasks 3. Allocate resources 4. Determine task duration including start and end dates. 5. Determine milestones 6. Construct the schedule 7. Determine the critical path 8. Set the baseline and obtain approval 9. Set quality gates 10. Establish the governance process