nerdexam
CompTIA

PK0-004 · Question #182

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

The correct answer is B. tasks. Below are the steps for creating a schedule according to certify: 1. Determine Tasks 2. Sequence Tasks 3. Allocate resources 4. Determine task duration including start and end dates. 5. Determine milestones 6. Construct the schedule 7. Determine the critical path 8. Set the…

Project life cycle phases

Question

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

Options

  • Adurations.
  • Btasks.
  • Ccritical path.
  • Dresources.

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    90% (47)
  • C
    2% (1)
  • D
    6% (3)

Explanation

Below are the steps for creating a schedule according to certify: 1. Determine Tasks 2. Sequence Tasks 3. Allocate resources 4. Determine task duration including start and end dates. 5. Determine milestones 6. Construct the schedule 7. Determine the critical path 8. Set the baseline and obtain approval 9. Set quality gates 10. Establish the governance process

Topics

#WBS#schedule development#task sequencing#project planning

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice