PK0-004 · Question #181
Two team members approach a project manager with different ideas for completing a task. After listening to the team members' ideas, the project manager does not choose either one and requires both…
The correct answer is C. Forcing. This should be "Forcing / Direct". We are not focusing much on common area's of agreement, we are requiring the team to do what the PM is asking.
Project management concepts
Question
Two team members approach a project manager with different ideas for completing a task. After listening to the team members' ideas, the project manager does not choose either one and requires both members to finish the task as originally planned. Which of the following conflict resolution techniques is the project manager applying?
Options
- AAvoiding
- BSmoothing
- CForcing
- DCompromising
How the community answered
(56 responses)- A4% (2)
- B2% (1)
- C93% (52)
- D2% (1)
Explanation
This should be "Forcing / Direct". We are not focusing much on common area's of agreement, we are requiring the team to do what the PM is asking.
Topics
#conflict resolution#forcing#team management#project manager