CompTIA
PK0-004 · Question #184
PK0-004 Question #184: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #184. The question stem and answer options stay visible for context.
Question
A project has a BAC of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
Options
- AAdd the required work to complete the project behind $892,500.
- BEvaluate the impact and justify adding new work to the project.
- CObtain approval from the CCB.
- DRequest a budget increase of $170,000.
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.