PK0-004 · Question #184
A project has a BAC of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the…
The correct answer is C. Obtain approval from the CCB. The project manager has identified and documented that certain key applications were not included in the scope management plan. Next step get approval from the CCB.
Question
A project has a BAC of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
Options
- AAdd the required work to complete the project behind $892,500.
- BEvaluate the impact and justify adding new work to the project.
- CObtain approval from the CCB.
- DRequest a budget increase of $170,000.
How the community answered
(27 responses)- A4% (1)
- B19% (5)
- C67% (18)
- D11% (3)
Explanation
The project manager has identified and documented that certain key applications were not included in the scope management plan. Next step get approval from the CCB.