nerdexam
ExamsPK0-004Questions#184
CompTIA

PK0-004 · Question #184

PK0-004 Question #184: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-004 to reveal the answer and full explanation for question #184. The question stem and answer options stay visible for context.

Question

A project has a BAC of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?

Options

  • AAdd the required work to complete the project behind $892,500.
  • BEvaluate the impact and justify adding new work to the project.
  • CObtain approval from the CCB.
  • DRequest a budget increase of $170,000.

Unlock PK0-004 to see the answer

You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-004 Practice