nerdexam
CompTIA

PK0-004 · Question #17

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?

The correct answer is A. Project charter. One of the most critical and essential documents for every project is the Project Charter. It lays down the foundation for the project.

Project life cycle phases

Question

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?

Options

  • AProject charter
  • BProject management plan
  • CProject statement of work
  • DProject schedule

How the community answered

(21 responses)
  • A
    95% (20)
  • D
    5% (1)

Explanation

One of the most critical and essential documents for every project is the Project Charter. It lays down the foundation for the project.

Topics

#project charter#initiation phase#project kickoff#first document

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice