CompTIA
PK0-004 · Question #17
A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?
The correct answer is A. Project charter. One of the most critical and essential documents for every project is the Project Charter. It lays down the foundation for the project.
Project life cycle phases
Question
A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?
Options
- AProject charter
- BProject management plan
- CProject statement of work
- DProject schedule
How the community answered
(21 responses)- A95% (20)
- D5% (1)
Explanation
One of the most critical and essential documents for every project is the Project Charter. It lays down the foundation for the project.
Topics
#project charter#initiation phase#project kickoff#first document
Community Discussion
No community discussion yet for this question.