The PMO is responsible for: (Choose two.),

The correct answer is C. setting standards and practices for the organization and providing governance. D. outlining consequences of non-performance and coordinating between disparate projects. The PMO functions as an organizational governance and oversight body rather than a direct project executor. Its core responsibilities are standardizing practices across projects and coordinating performance accountability.

Project management concepts

Question

The PMO is responsible for: (Choose two.),

Options

  • Amanaging the project plan, scope, risk, and budget.
  • Bcontributing expertise, deliverables, and estimates of costs.
  • Csetting standards and practices for the organization and providing governance.
  • Doutlining consequences of non-performance and coordinating between disparate projects
  • Eapproving funding, developing the project schedule, and gathering high-level requirements

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    85% (22)
  • E
    4% (1)

Why each option

The PMO functions as an organizational governance and oversight body rather than a direct project executor. Its core responsibilities are standardizing practices across projects and coordinating performance accountability.

Amanaging the project plan, scope, risk, and budget.

Managing project plan, scope, risk, and budget on a day-to-day basis is the responsibility of the individual project manager assigned to that project, not the PMO.

Bcontributing expertise, deliverables, and estimates of costs.

Contributing expertise, deliverables, and cost estimates is the role of project team members and subject matter experts, not a PMO function.

Csetting standards and practices for the organization and providing governance.Correct

The PMO establishes and enforces project management standards, methodologies, and governance frameworks organization-wide to ensure consistency and alignment with strategic objectives.

Doutlining consequences of non-performance and coordinating between disparate projectsCorrect

The PMO outlines consequences of non-performance and coordinates interdependencies between disparate projects, ensuring portfolio-level alignment and accountability.

Eapproving funding, developing the project schedule, and gathering high-level requirements

Approving funding and gathering high-level requirements is typically performed by the project sponsor or executive steering committee, not the PMO.

Concept tested: PMO roles and organizational governance responsibilities

Source: https://www.pmi.org/learning/library/pmo-types-governance-models-9652

Topics

#PMO#governance#standards and practices#portfolio coordination