Which of the following shows projected project expenditures?
The correct answer is A. Work breakdown structure. A WBS is one of the fundamental building blocks of project planning. It will be used as an input to numerous other planning processes. It's also the basis for estimating activity duration, assigning resources to activities, estimating work effort, and creating a budget.
Tools and documentation
Question
Which of the following shows projected project expenditures?
Options
- AWork breakdown structure
- BCash flow schedule
- CCash burn rate
- DBudget milestone
How the community answered
(33 responses)- A91% (30)
- B6% (2)
- C3% (1)
Explanation
A WBS is one of the fundamental building blocks of project planning. It will be used as an input to numerous other planning processes. It's also the basis for estimating activity duration, assigning resources to activities, estimating work effort, and creating a budget.
Topics
#WBS#project budget#expenditure tracking#cost management