A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: - Coordinate project schedule - Manage to the triple…

The correct answer is B. Strong matrix. A Strong Matrix, which is described as having a PMO but still having team members reporting to functional managers, hence the need to provide feedback to managers.

Project management concepts

Question

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

  • Coordinate project schedule
  • Manage to the triple constraint
  • Provide performance feedback to team members' managers

Which of the following types of organizational structures did the new project manager MOST likely join?

Options

  • ABalanced matrix
  • BStrong matrix
  • CFunctional
  • DProjectized

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    82% (31)
  • C
    11% (4)
  • D
    3% (1)

Explanation

A Strong Matrix, which is described as having a PMO but still having team members reporting to functional managers, hence the need to provide feedback to managers.

Topics

#strong matrix#organizational structure#project authority#triple constraint