A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: - Coordinate project schedule - Manage to the triple constraint - Provide performance feedback to team members' managers Which of the following types of organizational structures did the new project manager MOST likely join?
Options
- ABalanced matrix
- BStrong matrix
- CFunctional
- DProjectized