A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: - Coordinate project schedule - Manage to the triple…
The correct answer is B. Strong matrix. A Strong Matrix, which is described as having a PMO but still having team members reporting to functional managers, hence the need to provide feedback to managers.
Project management concepts
Question
A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:
- Coordinate project schedule
- Manage to the triple constraint
- Provide performance feedback to team members' managers
Which of the following types of organizational structures did the new project manager MOST likely join?
Options
- ABalanced matrix
- BStrong matrix
- CFunctional
- DProjectized
How the community answered
(38 responses)- A5% (2)
- B82% (31)
- C11% (4)
- D3% (1)
Explanation
A Strong Matrix, which is described as having a PMO but still having team members reporting to functional managers, hence the need to provide feedback to managers.
Topics
#strong matrix#organizational structure#project authority#triple constraint