nerdexam
CompTIA

PK0-004 · Question #151

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

The correct answer is C. Add tasks. After breaking the project into its individual components and documenting them in the WBS, the project manager can use the WBS to schedule all project activities. Creating the schedule is probably one of the most time-consuming tasks for any project because of the amount of…

Project life cycle phases

Question

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

Options

  • AAdd durations.
  • BAdd the start and finish dates
  • CAdd tasks.
  • DAdd resources.

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    91% (39)
  • D
    2% (1)

Explanation

After breaking the project into its individual components and documenting them in the WBS, the project manager can use the WBS to schedule all project activities. Creating the schedule is probably one of the most time-consuming tasks for any project because of the amount of coordination required in the process: 1. Determine the tasks. 2. Determine the project’s milestones. 3. Determine each task’s durations and start/finish dates. 4. Set predecessors and dependencies. 5. Sequence and prioritize the tasks. 6. Determine the critical path. 7. Allocate project resources to the individual tasks. 8. Set the schedule baseline. 9. Set the quality gates. 10. Set the governance gates.

Topics

#schedule development#task sequencing#project planning#WBS

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice