nerdexam
CompTIA

PK0-004 · Question #154

A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to…

The correct answer is A. Using the WBS will help prevent work from slipping or being forgotten. D. The WBS will aid in determining which resources are required for the project. A WBS best justifies itself to skeptical managers by demonstrating that it prevents overlooked work and clarifies resource requirements for the project.

Tools and documentation

Question

A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).

Options

  • AUsing the WBS will help prevent work from slipping or being forgotten.
  • BThe WBS will be required on very large projects.
  • CThe WBS will be required if the project manager has the time available to complete it.
  • DThe WBS will aid in determining which resources are required for the project.
  • EThe WBS is the best way to determine risks of the project.

How the community answered

(55 responses)
  • A
    93% (51)
  • B
    4% (2)
  • C
    2% (1)
  • E
    2% (1)

Why each option

A WBS best justifies itself to skeptical managers by demonstrating that it prevents overlooked work and clarifies resource requirements for the project.

AUsing the WBS will help prevent work from slipping or being forgotten.Correct

A WBS decomposes the total project scope into smaller, manageable work packages, ensuring every deliverable and task is explicitly documented, which directly prevents work items from being overlooked or falling through the cracks during execution.

BThe WBS will be required on very large projects.

Stating the WBS is required only on very large projects is an incorrect and artificially limiting claim that would not persuade managers to adopt it as a standard practice.

CThe WBS will be required if the project manager has the time available to complete it.

Conditioning WBS creation on the project manager's available time frames it as optional and low-priority, which undermines its value and provides no compelling business case for adoption.

DThe WBS will aid in determining which resources are required for the project.Correct

By breaking the project down into detailed work packages, the WBS makes it possible to identify and assign the specific human, material, and financial resources required for each component, giving managers visibility into resource planning.

EThe WBS is the best way to determine risks of the project.

While the WBS can inform risk identification by clarifying scope boundaries, the risk register and risk assessment processes are the primary tools for determining and managing project risks.

Concept tested: Work Breakdown Structure benefits and justification

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#WBS#work breakdown structure#resource planning#scope management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice