PK0-004 · Question #1058
A project team has encountered a delay in receiving parts from a supplier and wants an update on the progress of the resolution. Which of the following can be used to determine who is assigned to…
The correct answer is D. RACI. A RACI matrix (Responsible, Accountable, Consulted, Informed) is a responsibility assignment tool that maps project tasks and decisions to specific team members and roles. To determine who is assigned to resolve a supplier delay issue, the RACI chart is the correct reference…
Question
A project team has encountered a delay in receiving parts from a supplier and wants an update on the progress of the resolution. Which of the following can be used to determine who is assigned to resolve the issue?
Options
- ASWOT
- BKPI
- COrganizational chat
- DRACI
How the community answered
(46 responses)- A4% (2)
- B2% (1)
- C2% (1)
- D91% (42)
Explanation
A RACI matrix (Responsible, Accountable, Consulted, Informed) is a responsibility assignment tool that maps project tasks and decisions to specific team members and roles. To determine who is assigned to resolve a supplier delay issue, the RACI chart is the correct reference because it explicitly identifies who is Responsible for each task or issue. SWOT (A) is a strategic analysis tool for assessing strengths, weaknesses, opportunities, and threats - it does not assign individuals to tasks. KPIs (B) are Key Performance Indicators used to measure performance, not to identify task ownership. An organizational chat (C) is a communication tool, not an assignment or accountability document. The RACI matrix is precisely designed to answer the question 'who owns this?' making it the ideal tool in this scenario.