Which of the following are mandatory Scrum ceremonies that need to be carried out during a sprint?

The correct answer is B. Sprint planning, daily stand-up, review meeting, and retrospective. According to the Scrum Guide, there are exactly four official Scrum events (ceremonies) that occur within each sprint: Sprint Planning, the Daily Scrum (daily stand-up), the Sprint Review, and the Sprint Retrospective. Option A incorrectly includes a 'grooming session' (backlog…

Project management concepts

Question

Which of the following are mandatory Scrum ceremonies that need to be carried out during a sprint?

Options

  • ASprint planning, daily stand-up, review meeting, grooming session, and retrospective
  • BSprint planning, daily stand-up, review meeting, and retrospective
  • CDaily stand-up, review meeting, and kickoff meeting
  • DRelease planning, grooming session, daily stand-up, review meeting, and retrospective

How the community answered

(30 responses)
  • B
    93% (28)
  • C
    3% (1)
  • D
    3% (1)

Explanation

According to the Scrum Guide, there are exactly four official Scrum events (ceremonies) that occur within each sprint: Sprint Planning, the Daily Scrum (daily stand-up), the Sprint Review, and the Sprint Retrospective. Option A incorrectly includes a 'grooming session' (backlog refinement) as a mandatory ceremony - while backlog refinement is a recommended practice, it is not an official mandatory Scrum event. Option C incorrectly includes a 'kickoff meeting' (not a Scrum event) and omits Sprint Planning and Retrospective. Option D incorrectly includes 'release planning' and 'grooming session,' neither of which are mandatory Scrum ceremonies. Option B correctly lists all four and only the four mandatory Scrum events, making it the correct answer.

Topics

#Scrum#sprint ceremonies#Agile methodology#daily stand-up