PK0-003 · Question #78

Which of the following project plan components would include information regarding the management of issues?

The correct answer is A. Project Management Plan. The Project Management Plan is the comprehensive document that guides all aspects of a project, including how various management processes, like issue management, will be conducted.

Tools and documentation

Question

Which of the following project plan components would include information regarding the management of issues?

Options

  • AProject Management Plan
  • BHuman Resources Plan
  • CRisk Management Plan
  • DScope Management Plan

How the community answered

(42 responses)
  • A
    86% (36)
  • B
    2% (1)
  • C
    2% (1)
  • D
    10% (4)

Why each option

The Project Management Plan is the comprehensive document that guides all aspects of a project, including how various management processes, like issue management, will be conducted.

AProject Management PlanCorrect

The Project Management Plan is the overarching document that integrates all subsidiary management plans and specifies how the project will be executed, monitored, controlled, and closed, including how issues will be identified, analyzed, and resolved or escalated.

BHuman Resources Plan

The Human Resources Plan focuses on acquiring, developing, and managing the project team, not directly on the procedures for managing project issues.

CRisk Management Plan

The Risk Management Plan addresses uncertain future events that may impact the project, while issues are current problems that have already occurred.

DScope Management Plan

The Scope Management Plan defines how the project scope will be defined, validated, and controlled, not how general project issues are managed.

Concept tested: Project Management Plan components