PK0-003 · Question #79
Which of the following is an acknowledgement that risks may occur, but a response is in place to minimize the risk impact?
The correct answer is B. Mitigation. Mitigation is a risk response strategy that involves taking actions to reduce the probability of a negative risk occurring or lessening its impact if it does.
Question
Which of the following is an acknowledgement that risks may occur, but a response is in place to minimize the risk impact?
Options
- AAcceptance
- BMitigation
- CAvoidance
- DEnhancing
How the community answered
(49 responses)- A4% (2)
- B94% (46)
- C2% (1)
Why each option
Mitigation is a risk response strategy that involves taking actions to reduce the probability of a negative risk occurring or lessening its impact if it does.
Acceptance is a strategy where no active steps are taken to deal with a risk; it's simply acknowledged, and the consequences are borne if it occurs.
Mitigation involves taking steps to reduce the probability of a risk occurring or lessening the impact if it does occur, acknowledging the risk while actively preparing a response to minimize its effect and bring it to an acceptable level.
Avoidance is a strategy where the project team takes steps to eliminate the risk entirely by changing the project plan or scope.
Enhancing is a strategy used for positive risks (opportunities) to increase their probability or impact, not for negative risks.
Concept tested: Risk response strategies - mitigation