PK0-003 · Question #79

Which of the following is an acknowledgement that risks may occur, but a response is in place to minimize the risk impact?

The correct answer is B. Mitigation. Mitigation is a risk response strategy that involves taking actions to reduce the probability of a negative risk occurring or lessening its impact if it does.

Project management concepts

Question

Which of the following is an acknowledgement that risks may occur, but a response is in place to minimize the risk impact?

Options

  • AAcceptance
  • BMitigation
  • CAvoidance
  • DEnhancing

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    94% (46)
  • C
    2% (1)

Why each option

Mitigation is a risk response strategy that involves taking actions to reduce the probability of a negative risk occurring or lessening its impact if it does.

AAcceptance

Acceptance is a strategy where no active steps are taken to deal with a risk; it's simply acknowledged, and the consequences are borne if it occurs.

BMitigationCorrect

Mitigation involves taking steps to reduce the probability of a risk occurring or lessening the impact if it does occur, acknowledging the risk while actively preparing a response to minimize its effect and bring it to an acceptable level.

CAvoidance

Avoidance is a strategy where the project team takes steps to eliminate the risk entirely by changing the project plan or scope.

DEnhancing

Enhancing is a strategy used for positive risks (opportunities) to increase their probability or impact, not for negative risks.

Concept tested: Risk response strategies - mitigation

Topics

#risk management#risk mitigation#risk response