nerdexam
CompTIA

PK0-003 · Question #80

A project with a projected budget of $100,000 is 75% complete and has a CPI of .85. Which of the following is TRUE regarding this project?

The correct answer is B. The project is currently in cost overrun. The Cost Performance Index (CPI) measures the cost efficiency of budgeted resources; a CPI less than 1.0 indicates that the project is over budget or experiencing a cost overrun.

Project management concepts

Question

A project with a projected budget of $100,000 is 75% complete and has a CPI of .85. Which of the following is TRUE regarding this project?

Options

  • AMore project work than projected has been completed
  • BThe project is currently in cost overrun
  • CThe project EV is 63.75
  • D$85,000 has been spent in the project

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    70% (21)
  • C
    10% (3)
  • D
    17% (5)

Why each option

The Cost Performance Index (CPI) measures the cost efficiency of budgeted resources; a CPI less than 1.0 indicates that the project is over budget or experiencing a cost overrun.

AMore project work than projected has been completed

The statement that the project is 75% complete refers to schedule progress or physical completion, not necessarily that more work than projected has been completed. CPI relates to cost efficiency.

BThe project is currently in cost overrunCorrect

A CPI (Cost Performance Index) of less than 1.0 (in this case, 0.85) indicates that the project is performing poorly on cost, meaning that the actual cost for the work performed is greater than the budgeted cost, which signifies a cost overrun.

CThe project EV is 63.75

The Earned Value (EV) is calculated as % complete multiplied by the Budget at Completion (BAC), which is 0.75 * $100,000 = $75,000, not $63.75.

D$85,000 has been spent in the project

Given CPI = EV / AC, and EV is $75,000, then Actual Cost (AC) = EV / CPI = $75,000 / 0.85 which is approximately $88,235.29, not $85,000.

Concept tested: Earned Value Management - Cost Performance Index (CPI)

Topics

#earned value management#cost performance index#project performance#cost overrun

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice